A2 closure at Whitfield for bridge installation
Where possible, traffic heading to or from the Port of Dover is recommended to use the A20/M20.
A key milestone in construction of Fastrack takes place on the weekend of Friday 14 to Monday 17 July as a new 31.5m span bridge is installed across the A2 at Whitfield.
A short stretch of the A2 from the Whitfield roundabout to the Whitfield interchange (A256 junction) will be closed to all traffic from 9.00pm on Friday, 14 July to 5.00am on Monday, 17 July.
There will be a signed diversion via the White Cliffs Business Park (Honeywood Road and Honeywood Parkway) during the works to install the bridge. Where possible, traffic heading to or from the Port of Dover is recommended to use the A20/M20.
Latest Posts
Italy – additional HGV driving ban on the A22 Brenner motorway
According to information announced by the government commissioner for the province of Bolzano, the Austrian authorities have introduced an HGV driving ban...
Belgium: HGV traffic redirected to the main roads starting from November
From Monday, November 4, the local authorities of Steenokkerzeel, Kampenhout, Kortenberg and Herent introduce a route coordination scheme for HGV traffic...
Austria: new HGV driving bans on the A12, A13 and A14 motorways
The Austrian Federal Minister for Climate, Environment, Energy, Mobility, Innovation and Technology has issued a regulation introducing additional HGV...