A2 closure at Whitfield for bridge installation
Where possible, traffic heading to or from the Port of Dover is recommended to use the A20/M20.
A key milestone in construction of Fastrack takes place on the weekend of Friday 14 to Monday 17 July as a new 31.5m span bridge is installed across the A2 at Whitfield.
A short stretch of the A2 from the Whitfield roundabout to the Whitfield interchange (A256 junction) will be closed to all traffic from 9.00pm on Friday, 14 July to 5.00am on Monday, 17 July.
There will be a signed diversion via the White Cliffs Business Park (Honeywood Road and Honeywood Parkway) during the works to install the bridge. Where possible, traffic heading to or from the Port of Dover is recommended to use the A20/M20.
Latest Posts
Mont Blanc Tunnel Night Closures – Schedule Through August 2026
From today, night‑time traffic restrictions are in effect in the Mont Blanc Tunnel. The tunnel operator has published a forecast schedule of planned...
First Border Crossings Unblocked. Situation in the Balkans is Changing
After several days of truckers’ protests in the Balkans, the first signs of improvement have emerged. In North Macedonia, border crossings for freight...
Düsseldorf: Theodor-Heuss Bridge closed to heavy vehicles from February 1
From today (February 1, 2026), a full traffic ban applies on the Theodor-Heuss Bridge in Düsseldorf for vehicles with a gross vehicle weight exceeding 3.5...